NTPC, the country's largest power producer has successfully completed trial operation of Unit-2 of 660 MW capacity of Tanda Super Thermal Power Station, Stage-II (2 x 660 MW) and consequently included in the installed capacity of NTPC Group with effect from Mar.31, 2021.
With this, the total installed capacity of NTPC and NTPC group has become 52385 MW and 65810 MW respectively.
NTPC has recorded its highest ever group generation of 314 BU in FY21, a growth of 8.2% compared to previous year. On a standalone basis, the company generated 270.9 BU in FY21, an increase of 4.3% over the previous year.
NTPC group recorded highest ever single day generation of 1192.42 MU (Group) & 990.65 MU (NTPC). The coal plants registered a PLF of 66% with an Availability factor of 91.43%.
Shares of the company declined Rs 0.15, or 0.14%, to settle at Rs 105.95. The total volume of shares traded was 421,709 at the BSE (Tuesday).