Larsen & Toubro (L&T) has successfully commissioned and handed over the state-of-the-art 360 MW Bheramara Combined Cycle Power Plant Development Project to North West Power Generation Company (NWPGCL), a fully owned subsidiary of Bangladesh Power Development Board (BPDB), on January 5, 2018. After performance testing, the plant capacity has been declared as 410 MW by the customer.
 
This power plant is based in Bheramara of Kushtia District in the western sector of Bangladesh, which is approximately 250 km from Kolkata, India.

L&T's scope of work included design, engineering, supply, installation and commissioning of the complete power plant on a back-to-back turnkey basis for Marubeni Corporation of Japan, with Gas Turbines, Steam Turbine and Generators from Mitsubishi Hitachi Power Systems, Japan. Work on this Japan International Cooperation Agency (JICA)-funded project had started in July 2014 and the power plant was partly commissioned earlier in Open Cycle, which was handed over to NWPGCL for commercial operation in May 2017.

Shailendra Roy, CEO & Managing Director, L&T Power & Whole-Time Director, L&T, said, ''The fact that two power plants were commissioned in quick succession in Bangladesh, one in December 2017 and the other in January 2018, speaks volumes about L&T's scale of operations. We thank the Bangladesh authorities for reposing faith in our capabilities.''

This project has been executed by the Gas Based Power Projects Business Unit of L&T, based out of Vadodara. L&T’s well-established strengths in design, engineering and construction, combined with robust quality and safety standards and on-time delivery, are vital contributors to its success in the power sector.

L&T has executed several large gas-based power projects on EPC basis for government utilities and independent power producers in India and abroad. In Bangladesh, L&T has recently completed and handed over the 225 MW Sikalbaha Combined Cycle Power Plant to BPDB in December 2017. It is currently executing two more gas-based power projects in Bangladesh-400 MW Bibiyana III Combined Cycle Power Project and 400 MW Bibiyana South Combined Cycle Power Project of BPDB.



Larsen & Toubro Limited   (Q,N,C,F)*

Comments Post comment 
 Post Comment
Name Email
Comment
Security Code type    into this box
Company Update
Zydus Cadila receives USFDA nod for Arsenic Trioxide injection - 15-Nov-2018 10:11
ICICI Bank raises retail term-deposit interest rates by upto 25bps - 15-Nov-2018 09:55
Lupin gets approval for Budesonide inhalation suspension - 13-Nov-2018 13:36
Suven Life Sciences secures 2 overseas product patents - 13-Nov-2018 10:18
GAIL Gas signs MoU with Energy Efficiency Services - 13-Nov-2018 10:14
Lupin launches generic Atovaquone oral suspension in US - 12-Nov-2018 16:06
Zydus Cadila gets USFDAs nod for anti-fungal ointment - 12-Nov-2018 13:40
NHB sanctions Rs 35 bn refinance facility to PNB Housing Finance - 12-Nov-2018 13:17
BHEL commissions 120 MW Pulichintala hydro-electric project - 12-Nov-2018 12:55
Tata Consultancy Services partners with ENGIE Laborelec - 12-Nov-2018 12:52
Lupin gets establishment inspection report for Nagpur unit - 12-Nov-2018 09:56
more...
Home  |   Shares  |   F&O  |   Mutual Funds  |   Loans  |   Insurance  |   News Centre
Wealth Tracker  |   Newsletters  |   Tax Corner  |   NRI Centre  |   Advertise
© All rights reserved. IRIS Business Services Limited
A Disclaimer